Manage project issues

While organisations will typically have their own definition of issues, an issue is generally defined as something that has already occurred and requires active management to control its impact on the project.

Effective issue management requires that each issue is:

  • Clearly defined
  • Assigned to a responsible individual
  • Actively managed to resolution within a defined timeframe

Creating a New Issue

  1. Ensure the relevant project is open
  2. Navigate to Tracking → Issues
  3. Select + New Issue
  4. Enter the Name

Important:
The Name field is mandatory and should be clear and concise to support identification across screens, reports, and dashboards.

The Assigned To and Due Date fields should not be left blank to ensure effective tracking and reporting.

  1. Complete the remaining fields as required
  2. Select Save & Close

Updating Issue Items

  1. Ensure the relevant project is open
  2. Navigate to Tracking → Issues
  3. Select the issue to update
  4. Update the required fields
  5. Select Save & Close

Exporting Issue Data

Issue data can be exported for reporting or analysis purposes. However, behaviour differs depending on where the data is accessed.


Export from the Project (Issue Register)

  1. Navigate to Tracking → Issues within the project
  2. Locate the ellipsis (… ) in the command bar of the issue register
  3. Select Export to Excel
  • The Issues tab is a subgrid, meaning:
    • Columns and filters cannot be customised
    • Only the visible fields in the register will be exported

Important:
The project-level issue register export will only include the fields visible in the grid and may not contain all relevant details for each issue.


Export from the Central Issue List

For full control over reporting and export:

  1. Navigate to Work → Issues
  2. Change the view from My Active Issues to All Active Issues
  3. Adjust the view as required:
    • Add or remove columns
    • Apply filters (e.g. by status, owner, due date)
  4. Save the updated view for reuse
  5. From the command bar:
    • Select Export to Excel, or
    • Use the ellipsis (… ) if required

Tip:
Exporting from the central Issues list allows you to customise the dataset and capture all relevant fields, making it more suitable for reporting, analysis, and audit purposes.


Reuse Across Other Registers

Tip:
This same export approach for Risks and Issues applies to other registers in Altus, including:

  • Dependencies
  • Deliverables
  • Decisions
  • Changes
  • Lessons

These are also exposed as central lists under the Work area and as subgrids within project, program, or portfolio records, where the same limitations and export patterns apply:

  • Subgrid = simple export (what you see is what you get)
  • Central list = flexible export (customise columns, filters, and views)

Key Considerations

  • Issues should be actively monitored until closure
  • Ownership and due dates are critical for resolution
  • Regular updates ensure visibility and control
  • Use the central list for reporting when full visibility is required