Create a resource plan from the schedule
The Resource Plan in Altus allows project managers to define resource demand by specifying:
- Required resources (Generic or Named)
- Effort across time periods (hours or FTE)
or fulfilment through the Resource Demand process. Once fulfilled, the committed allocations are reflected back into the Resource Plan.
Where This Is Performed
- Project → Resource Plan
Important: Purpose of the Resource Plan
The Resource Plan serves as the single source of truth for resource demand, enabling:
- Structured resource requests across time
- Alignment between project delivery and capacity
- Integration with Resource Demand and availability management
Option: Create Plan from Schedule
The Create Plan from Schedule feature allows you to generate a resource plan based on task assignments.
To create a resource plan from a schedule:
- Ensure your project schedule includes:
- Start Date
- End / Finish Date
- Effort
- Duration
- At least one task assignment with an Altus resource
- Navigate to Project → Resource Plan
- Select Data → Create Plan from Schedule
This will:
- Import resource assignments from Tasks
- Create Resource Plan entries aligned to the schedule
- Populate effort at a detailed (day-level) granularity
Important: When to Use “Create Plan from Schedule”
Important:
This feature is intended as a one-off starting point during the planning phase, not an ongoing synchronisation mechanism.
- Each time it is run, it attempts to create new Resource Plan data
- It should be used to initialise the plan, then maintained manually afterward
Behaviour When Creating from Schedule
- If no task assignments exist → no data is created
- If draft or proposed data exists → you will be prompted to overwrite
- If committed data exists → you must delete it before re-running
Adding and Managing Resource Requests
You can create or update resource demand directly in the Resource Plan.
Project managers typically:
- Add generic roles (e.g. Business Analyst)
- Add named resources where known
- Define approval ownership (e.g. pool owner or team manager)
Entering Proposed Effort
- Enter effort across time using:
- Hours, or
- FTE
Important:
- Only named resources display availability (based on calendars)
- Generic roles do not have availability constraints
As effort is entered:
- Values are shown in the Proposed column
- Hovering over values reveals additional details and status
Saving vs Submitting Resource Requests
There is a key distinction in how data is processed:
Save
- Stores the data
- Keeps status as Draft
- Does NOT notify resource managers
Submit and Save
- Changes status to Submitted
- Sends request to the appropriate manager
- Triggers fulfilment in the Resource Demand view
Important:
Resource requests must be submitted (not just saved) to be visible for fulfilment.
Understanding Request Statuses
Each time period within a resource plan can have a status:
- Draft – saved but not submitted
- Submitted – sent for fulfilment
- Approved – fulfilled as requested
- Set by approver – fulfilled with a different resource
Status Behaviour
- Editing a submitted request changes it back to Draft
- Submitting again re-sends it for fulfilment
- Status is visible when hovering over values
Viewing Committed Allocations
Once resource managers fulfil the request:
- Values appear in the Committed column
- You may see:
- Original requested resource fulfilled
- Substitute resources assigned
- Split allocations across multiple resources
Important:
- “Approved” indicates the requested resource was assigned
- “Set by approver” indicates an alternative resource was allocated
Using Comments
Comments provide a way to communicate with resource managers.
- Add context to requests
- Indicate priority or constraints
- Respond to fulfilment decisions
Important:
Comments are not a chat system — they are a record of decisions and communication.
Updating the Resource Plan
After fulfilment:
You can:
- Increase or decrease demand
- Add new resource requests
- Adjust time-based allocations
Any changes:
- Reset affected values to Draft
- Require re-submission
Tip:
Treat the Resource Plan as a living document that evolves with the project.
How This Connects to Resource Demand
The workflow operates as follows:
- Project Manager creates resource requests (Resource Plan)
- Requests are submitted for fulfilment
- Resource Manager fulfils demand (Resource Demand / Heatmap)
- Allocations appear back in the Resource Plan as committed work
Tips
- Use Create Plan from Schedule only as an initial setup tool
- Always use Submit and Save to trigger fulfilment
- Review committed allocations regularly
- Use comments to guide fulfilment decisions
- Monitor changes as updates will require re-submission
- Be mindful of named resource availability when requesting effort